Galeão Airport (SBGL/GIG)

Galeão Airport (SBGL/GIG) was granted to the private initiative in an auction held on BM&BOVESPA on November 22nd, 2013.

Concessionaire: RIOgaleão

Website: http://www.riogaleao.com/

Concession object: Concession of the public services for the expansion, maintenance and exploration of the infrastructure of the airport complex.

Date of contract signature: April 2nd, 2014

Start of concession: May 7th, 2014

Concession term: 25 years

Investments and works

  • April 2nd, 2014 – Concession contract signature
  • May 7th, 2014 – Effective date of contract
  • December 31st, 2014 – Delivery of mandatory investments:
    • Implementation of runway end safety areas
  • February 2nd, 2015 – End of Phase IA. Transfer of operations from the Brazilian Airport Infrastructure Company (Infraero) to the concessionaire.
  • December 31st, 2015 – Delivery of mandatory investments:
    • Adequacy of runways systems for F-Code aircrafts
    • Access roads and parking lots with minimum 1,850 additional spaces
  • April 30th, 2016 – Start of Phase IB. Delivery of mandatory investments and recovery of service level
    • Expansion of passenger terminal with 26 additional boarding bridges
    • Patio for 97 aircrafts
  • May 1st, 2016 – Start of Phase II
    • Maintenance of service level
    • Investment triggers
  • Rio 2016 Summer Olympic Games. Delivery of mandatory investments:
    • Adequacy of facilities for cargo storage in compliance with the commitments made to the International Olympic Committee
  • December 31st, 2016 – Delivery of mandatory investments:
  • Obstacle removal and providing of graded area of runway and taxiways strips, according to the critical operation for airplanes which the runway and taxiways are intended to serve
  • December 31st, 2018 - Delivery of mandatory investments:
    • Implementation of runway end safety areas
  • 262.900 mov. / year demand – Delivery of mandatory investments:
    • Landing and takeoff runway, with 3,000m length, for E-Code aircrafts.
  • May 7th, 2039 – End of Phase II.