Florianopolis Airport (SBFL/FLN)

Florianopolis Airport (SBCF/CNF) was granted to the private initiative in an auction held on BM&BOVESPA on March 16th, 2017.

Concessionaire: Concessionária do Aeroporto Internacional de Florianópolis S.A

Website: https://floripa-airport.com/

Concession object: Concession of the public services for the expansion, maintenance and exploration of the infrastructure of the airport complex.

Date of contract signature: July 28th, 2017

Start of concession: August 31st, 2017
(with the knowledge by the concessionaire of the issuance of the Service Order, issued up to 30 days after the publication of the extract of the contract in the Brazilian federal register publication)

Concession term: 30 years

Investments and works

  • July 28th, 2017 – Concession contract signature
  • August 31st, 2017 – Effective date of contract
  • April 3rd, 2018 – End of Phase IA. Transfer of operations from the Brazilian Airport Infrastructure Company (Infraero) to the concessionaire
  • October 31st, 2019 – End of Phase IB. Delivery of mandatory investments:
    • Construction of new terminal with capacity to simultaneously process 1,330 domestic and 370 international boarding passengers; 1,290 domestic and 310 international arriving passengers
    • Patio for 16 aircrafts, with 10 parking positions to be served by boarding bridges
    • Access roads and parking lots to serve at least 2,300 spaces
    • Implementation of runway end safety areas
    • Adjustment of shoulders and graded areas of runway and taxiway strip of PPD 14/32
    • Adjustment of graded areas of runway and taxiway strip of PPD 03/21
    • Adjustment of taxiways, its shoulders and taxiways strips
    • Extension of PPD 14/32 to minimum 2,400m length
    • Implementation of taxiway parallel to the south with right link to thresholds of PPD 14/32
    • Automated baggage safety management and inspection system, capable of inspecting 100% of checked baggage.
    • Cargo security inspection system, able to inspect 100% of the cargo shipped with international destination.
  • November 1st, 2019 – Start of Phase II
    • Maintenance of service level
    • Investment triggers
  • August 31st, 2047 – End of Phase II.