Viracopos Airport (SBKP/VCP)

Viracopos Airport (SBKP/VCP) was granted to the private initiative in an auction held on BM&BOVESPA on February 6th, 2012.

Concessionaire: Aeroportos Brasil Viracopos

Website: http://www.viracopos.com/

Concession object: Concession of the public services for the expansion, maintenance and exploration of the infrastructure of the airport complex.

Date of contract signature: June 14th, 2012

Start of concession: July 11th, 2012

Concession term: 30 years

Investments and works

  • June 14th, 2012 – Concession contract signature
  • July 11th, 2012 – Effective date of contract
  • February 14th, 2013 – End of Phase IA. Transfer of operations from the Brazilian Airport Infrastructure Company (Infraero) to the concessionaire
  • May 11th, 2014 – End of Phase IB. Delivery of mandatory investments:
    • Passenger terminal with capacity to simultaneously process 1,550 boarding and 1,550 arriving passengers
    • Patio for 35 aircrafts, with 28 parking positions to be served by boarding bridges
    • Access roads and parking lot with 4,500 spaces
    • Obstacle removal and providing of graded area of runway and taxiways strips, according to the critical operation for airplanes which the runway and taxiways are intended to serve
  • May 12th, 2014 – Start of Phase IC. Recovery of service level
  • May 12th, 2016 – End of Phase IC. Recovery of service level
  • May 13th, 2016 – Start of Phase II
    • Maintenance of service level
    • Investment triggers
  • December 31st, 2018 – Delivery of mandatory investments:
    • Implementation of new runway end safety areas
  • 178.000 mov. / year demand or end of Phase II – Delivery of mandatory investments:
    • Construction of second runway, with 3,600m length.
  • 351.000 mov. / year demand or end of Phase II – Delivery of mandatory investments:
    • Construction of third runway, with 2,600m length.
  • Reaching 456.000 mov. / year – Delivery of mandatory investments:
    • Construction of fourth runway, with 2,200m length
  • July 11th, 2042 – End of Phase II