Você está aqui: Página Inicial > Concessions > Salvador Airport (SBSV/SSA)
conteúdo

Brasilia Airport (SBBR/BSB)

Salvador Airport (SBSV/SSA) was granted to the private initiative in an auction held on BM&BOVESPA on March 16th, 2017.

Concessionaire: Concessionária do Aeroporto de Salvador S.A. - CASSA

Website: http://brasil.vinci-airports.com

Concession object: Concession of the public services for the expansion, maintenance and exploration of the infrastructure of the airport complex.

Date of contract signature: July 28th, 2017

Start of concession: August 31st, 2017
(with the knowledge by the concessionaire of the issuance of the Service Order, issued up to 30 days after the publication of the extract of the contract in the Brazilian federal register publication)

Concession term: 30 years.

Investments and works

  • July 28th, 2017 – Concession contract signature.
  • August 31st, 2017 – Effective date of contract.
  • April 2nd, 2018 – End of Phase IA. Transfer of operations from the Brazilian Airport Infrastructure Company (Infraero) to the concessionaire.
  • October 31st, 2019 – End of Phase IB. Delivery of mandatory investments:
    • Expansion of passenger terminal with capacity to simultaneously process 1,770 domestic and 440 international boarding passengers; 1,830 domestic and 360 international arriving passengers.
    • Patio for 26 aircrafts, with 17 parking positions to be served by boarding bridges.
    • Access ways and parking lot to attend at least 1,630 spaces.
    • Implementation of runway end safety areas.
    • Adjustment of shoulders, taxiway strip and graded areas of PPD 10/28.
    • Adjustment of taxiway strip and graded areas of PPD 17/35.
    • Adjustment of taxiways, shoulders and taxiways strips.
    • Adjustment of separating distance between taxiway A center line and PPD 10/28 center line.
    • Automated baggage safety management and inspection system, capable of inspecting 100% of checked baggage.
    • Cargo security inspection system, able to inspect 100% of the cargo shipped with international destination.
  • November 1st, 2019 – Start of Phase IC. Delivery of mandatory investments:
    • Recovery of service level.
    • Increase processing capacity of passenger terminal: new contract demand.
    • Patio for 27 aircrafts, with 19 parking positions to be served by boarding bridges
    • Expand capacity of parking lots and access ways to 2,100 spaces.
  • 124.000 mov. / year – Prescriptive investment.
    • New runway with 2,160m, for F-Code aircrafts, parallel to runway 10/28 for parallel and independent approaches in IFR operations.
  • November 1st, 2021 – End of Phase IC.
  • November 2nd, 2021 – Start of Phase II.
    • Maintenance of service level.
    • Investment triggers.
  • August 31st, 2047 – End of Phase II.